Operator Qualification (OQ)
What is OQ?
The Operator Qualification Rule is part of 49CFR Part 192 (subpart
N) and 49CFR Part 195 (subpart G) under the Department of Transportation,
Office of Pipeline Safety. This rule requires pipeline operators
to develop and maintain a written qualification program for individuals
performing covered tasks on pipeline facilities.
What are the key dates associated with OQ?
October 26, 1999 OQ rule went into effect
April 27, 2001 Operators must have a written qualification
program
October 28, 2002 Operators must complete the qualification
of individuals performing covered tasks
What is H&M required to
do under OQ?
The rule applies only to operators. H&M is not required to
do anything under the rule. H&M is required to meet the requirements
our customers specify in their contracts with us. These contractual
requirements will be 1) provide "qualified" workers,
and 2) keep records of each worker and his/her qualification
to perform covered tasks. Our Action Plan details how we will comply with our customer's OQ plan.
What is a covered task?
A covered task is an activity, identified by the operator (our
customer) that:
Is performed on a pipeline facility
Is an operations or maintenance task
Is performed as a requirement of this part
Affects the operation or integrity of the pipeline
New construction work does not
fall under this rule.
What is H&M now doing to get ready for OQ?
Henkels & McCoy joined the Energy Training Network
Qualified For One Qualified For All consortium
in March of 1999. This consortium is made up of pipeline operators
and contractors who have a common interest in maximizing the
benefits of OQ while keeping costs as low as possible. The consortium
members agree to accept a common Covered Task List and to accept
the qualifications of each other's workers, through a common
data base, to perform covered tasks.
H&M personnel participated in the ETN Covered Task
identification process for the Q41 consortium.
We developed an OQ Action Plan that detail's how we will comply
with our customer's OQ plan.
• We are using the Q41 records program, OQPlus, and are developing the
procedures necessary to allow our customers to access the records they
require for OQ compliance.
Our Sales and Operations people take every opportunity
available to discuss OQ with customers and prospective customers.
This exchange of ideas and developments will keep H&M at
the forefront of OQ compliance.
• We have more than 100 trained Evaluators and are certifying our work
force on the required covered tasks. We are also using the MEA/ETN
Training Modules where required.
How do these steps help our customer?
Our goal is, and always has been, to be prepared to provide quality
service to our customers. In the past, this has meant maintaining
a trained work force equipped with the necessary tools and equipment
to meet the needs of our customers. Today, this also means being
knowledgeable of, and prepared to satisfy, the requirements of
the Operator Qualification rule.
What more can/should H&M
do to meet our customer's expectations of contractor OQ compliance?
Take every opportunity to discuss this issue with customers and
prospective customers. Share the answers received with our pipeline
operations, sales, and headquarters people to help H&M become
the contractor industry expert on OQ.
How do I get more information
on OQ?
The entire OQ Rule can
be found on the web at http://ops.dot.gov/regulate.htm under
the title "Pipeline Safety: Qualification of Pipeline Personnel,
49 CFR Parts 192 and 195 Final rule".
|